Investor
“Siemens” LLC Belgrade, Serbia
End user
“Shanghai Electric Power Co. Ltd.”, Shanghai, China
Project realization (completion) year
2018
State
Montenegro
Design, delivery of equipment and execution of electrical installation works on the construction of the Mozura Wind Farm – construction of the SS 110/30 kV “Mozura”.
Design, delivery of equipment and execution of construction and electrical installation works of the 110 kV transmission line Bar-Ulcinj for the connection of WF Mozura to the electrical grid.
SS 110/30 kV “Mozura”
110 kV transmission line Bar-Ulcinj