Description of works:
Reconstruction of SS 35/10 kV “Metaljka” for power supply of auxiliary equipment on external facilities RHPP-Phase 2: Installation of 2 transformers 35/10 kV 4MVA, installation of insulated facility 35 kV and installation of air-insulated facility 10 kV.